. Construct the project network (5 marks) B. Calculate, ES, EF. LS, LF, Slack, critical path and project duration.

Fatima has done detailed planning regarding a project, King Khalifa dinner, the tasks to be performed, their immediate predecessors, and their estimated durations are as follows:

Activity Activity Description Estimated Duration Immediate predecessors
A Select location 2 weeks
B Obtain keynote Speaker 1 week
C Obtain other speakers 2 weeks B
D Make travel plan for keynote speakers 2 weeks A, B
E Make travel plan for other speakers 3 weeks A, C
F Make food arrangements 2 weeks A
G Negotiate hotel rates 1 week A
H Prepare brochure 1 week C, G
I Mail brochure 1 week H
J Take reservations 3 weeks I
K Prepare handouts 4 weeks C, F

From the above information:

A. Construct the project network (5 marks)
B. Calculate, ES, EF. LS, LF, Slack, critical path and project duration.