14 put the following steps in order for using the high low method of estimating a co 4309434
14) Put the following steps in order for using the high-low method of estimating a cost function:
A = Identify the cost function
B = Calculate the constant
C = Calculate the slope coefficient
D = Identify the highest and lowest observed values
A) D C A B
B) C D A B
C) A D C B
D) D C B A
15) Regression analysis:
A) is simple to compute
B) measures the change in a dependent variable associated with one or more independent variables
C) is mathematical so it does not require an understanding of operations
D) uses the constant to measure goodness of fit
16) Simple regression differs from multiple regression in that:
A) multiple regression uses all available data to estimate the cost function, whereas simple regression only uses simple data
B) simple regression is limited to the use of only the dependent variables and multiple regression can use both dependent and independent variables
C) simple regression uses only one independent variable and multiple regression uses more than one independent variable
D) simple regression uses only one dependent variable and multiple regression uses more than one dependent variable
17) The slope of the line of regression is the:
A) rate at which the dependent variable varies
B) rate at which the independent variable varies
C) level of total fixed costs
D) level of total variable costs
Answer the following questions using the information below:
The Delmonico Company uses the high-low method to estimate the cost function. The information for 2011 is provided below:
Machine-hoursLabor Costs
Highest observation of cost driver400$20,000
Lowest observation of cost driver240$ 13,600
18) What is the slope coefficient per machine-hour?
A) $56.66
B) $0.10
C) $40.00
D) $50.00
19) What is the constant for the estimating cost equation?
A) $4,000
B) $13,600
C) $16,000
D) $20,000
20) What is the estimate of the total cost when 300 machine-hours are used?
A) $4,000
B) $8,000
C) $12,000
D) $16,000
Answer the following questions using the information below:
The Ranger Company uses the high-low method to estimate it's cost function. The information for 2011 is provided below:
Machine-hours Costs
Highest observation of cost driver2,000$450,000
Lowest observation of cost driver1,000$ 250,000
21) What is the slope coefficient per machine-hour?
A) $250.00
B) $25
C) $20.00
D) $200.00
22) What is the constant for the estimating cost equation?
A) $250,000
B) $450,000
C) $50,000
D) $0
23) What is the estimate of the total cost when 1,100 machine-hours are used?
A) $250,000
B) $270,000
C) $300,000
D